Up webNB Home Page Contents News LinksHBVC Diary

 

Next Meeting/events:

8/12/99 7.45 at Apollo Centre Halesworth

Here is my summary of where the Centre for the Community is at:
Last year: 2 day Postit event (Heart of Halesworth) held at the library to get peoples requirements
Jan 98 Invites sent to "all" local groups asking for their requirements.
13/1/98 Health & social providers meeting to discuss requirements. Main requirement is a single point for information.
30/1/98 Ezra has sent a letter to Waveny council to get their invlovement - and ask for some money.
(There was a mention in the EADT on 3/2/98 about Waveny council & the centre.)
4/2/98 Draft feasibility study brief, is available for review; based on
, recommended to us by Suffolk ACRE. suffolk ACRE

An initial paper sort of possible architect portfolios for project has been done.

11/2/98 Invites sent to short-listed architects, including agreed feasibility study brief.
3/3/98 Preparation meeting for architects presentations.
4/3/98 The architects gave their presentations for the feasibility study work.
We have selected Architype, the Morrocco Store, London to go into further detail with
18/3/98 Meeting with Architype to agree deliverables, plans, costs etc
8/4/98 How to get funding - actions given out.
29/4/98 Review progress. 8pm at World Land Trust meeting room
1/11/98 Meeting at Walpole to arrange Halesworth Regeneration open day presentation.
11/11/98 Display at Halesworth Library - 3 days
24/11/98 Initial Feasibility Meeting with Architype at the Apollo Centre 7.30pm
All funding available. Actions to get bank account, provide contact lists and site details.
4/2/99 Requirements capture brainstorming event with local key groups
The fesibility study complete
20/8/99 Joined Suffolk ACRE
29th Aug Stand at Halesworth Antiques Fair
5th Sept Stand at Greenpeace fair
 

 

Copyright © 1999 webNB   webnb@BTInternet.com